DTEK CEO Maksym Tymchenko said Kyiv can maintain electricity supply to critical infrastructure even under the worst-case scenario. He warned that continued attacks at the intensity of the past two months could leave businesses without power and residents with only two to three hours of electricity per day.

Key points

  • DTEK CEO Maksym Tymchenko said Kyiv can maintain electricity supply to critical infrastructure even under the worst-case scenario.
  • If Russia continues attacking Kyiv at the intensity of the past two months, residents could receive only two to three hours of electricity per day and businesses could be unable to operate.
  • Russia used a reactive drone with a charge to destroy high-voltage supports for the first time in late September, followed by strikes that stopped Kyiv's metro and water supply.
  • An expert estimated that only 200 MW of the 1.5 GW of generation needed by Kyiv would be launched by the end of the year, enough only for critical infrastructure.
  • A DTEK thermal power plant halted generation after heavy shelling on October 23; restoring damaged plants was estimated at 300 million euros.
  • DTEK covered about half of the restoration costs and plans to raise roughly 150 million euros externally for the 2026–2027 heating season.
  • On October 28, President Zelensky instructed Prime Minister Serhii Koretskyi to form a special team to strengthen Kyiv's resilience.

Why it matters

Keeping critical infrastructure powered is central to maintaining essential services in Kyiv during intensified attacks. At the same time, continued damage to generation and transmission facilities could deepen electricity shortages, restrict business activity and require years to rebuild the power system.

What happened

DTEK CEO Maksym Tymchenko said the company believes Kyiv can keep critical infrastructure powered even in a worst-case energy scenario. He also warned that if Russian attacks continue at the intensity of the previous two months, residents may receive no more than two to three hours of electricity per day and businesses may be unable to operate. The warning comes after Russia deployed a reactive drone with a charge against high-voltage supports for the first time in late September and subsequent strikes disrupted Kyiv's metro and water supply. A DTEK thermal power plant stopped generating electricity after a heavy barrage on October 23. The company estimates that restoring its damaged plants will cost 300 million euros, has covered about half of that amount itself, and plans to raise around 150 million euros from external sources for preparations for the 2026–2027 heating season.

How Ukrainian sources describe it

Ukrainian reporting focuses on Kyiv's ability to maintain critical services under severe attack conditions while warning of severe restrictions for residents and businesses. The reporting also examines damage to energy infrastructure, regional imbalances in electricity supply, recovery timelines, repair costs and preparations for the coming heating season, alongside a public dispute over the capital's resilience record.

Where reporting differs

President Zelensky said on October 13 that frontline regions were implementing resilience plans more effectively than Kyiv. Kyiv Mayor Vitali Klitschko rejected that assessment as unfounded and described attempts to remove local heads and replace them with military administration leaders as pressure on local self-government.

Background

Russia is seeking to divide Ukraine's unified energy system into separate parts. Western regions may experience fewer outages because they have nuclear and coal generation and access to electricity imports, while central and eastern regions may face greater consequences from higher consumption and limited transmission capacity from the west. An expert estimated that full restoration of the energy system could require five years. From late February to early March 2026, Zelensky asked adviser Oleksandr Kubrakov to help with Kyiv's energy issues.